Monthly Construction and Environmental Update June 2009
June 29, 2009

Escatawpa to Jones Road (8,650’) –
• Base and pave project complete through this section.
• Area stabilized with permanent BMPs.

Jones Road to Walter Tanner Road (10,650’) –
• Base and pave project complete through this section.
• Area stabilized with permanent BMPs.

Walter Tanner Road to Wilmer-Georgetown Road (4,186’) –
• Construction of roadways, drain pipes, sediment basins, and ditch lines from Walter Tanner Road to Wilmer Georgetown Road (Station 250 to 281) complete.
• Area stabilized with permanent BMPs.

Wilmer-Georgetown Road to Glenwood Road (13,617’) –
• Constructions of roadways, drain pipes, sediment basins, and ditch lines from Wilmer Georgetown Road to Big Creek bridges (Station 288 to 400) complete.
• Area stabilized with permanent BMPs.
• Automatic water samplers installed to monitor water quality coming onto and discharging from project into Long Branch and Big Creek.

Glenwood Road to east end of project (4,964’) –
o Construction of roadways, drain pipes, sediment basins, and ditch lines east from Glenwood Road (Station 424 to 469) complete.
o Completed roadway sections have been capped with small aggregate for access travel or covered with top soil, seeded, mulched, and netted with erosion control blankets.
o Temporary and permanent BMPs installed to help prevent erosion and contain sediment.
o Automatic water samplers installed to monitor water quality coming onto and discharging from project into Collins Creek.

Environmental Issues:
- Rain Days: June 4 (0.86 ave.”), June 5 (0.42 ave.”). Total of 1.28 inches of rain this month. No Non-Compliant conditions or Water Quality violations.