Monthly Construction and Environmental Update July 2009
July 31, 2009

Monthly Construction and Environmental Update
July 2009

Escatawpa to Jones Road (8,650’) –
• Base and pave project complete through this section.
• Area stabilized with permanent BMPs.

Jones Road to Walter Tanner Road (10,650’) –
• Base and pave project complete through this section.
• Area stabilized with permanent BMPs.

Walter Tanner Road to Wilmer-Georgetown Road (4,186’) –
• Construction of roadways, drain pipes, sediment basins, and ditch lines from Walter Tanner Road to Wilmer Georgetown Road (Station 250 to 281) complete.
• Area stabilized with permanent BMPs.

Wilmer-Georgetown Road to Glenwood Road (13,617’) –
• Construction of roadways, drain pipes, sediment basins, and ditch lines from Wilmer Georgetown Road to Big Creek bridges (Station 288 to 400) complete.
• Area stabilized with permanent BMPs.

Glenwood Road to east end of project (4,964’) –
• Construction of roadways, drain pipes, sediment basins, and ditch lines east from Glenwood Road (Station 424 to 469) complete.
• Area stabilized with permanent BMPs.

Environmental Issues:
- Rain Days: July 4 (0.66”avg), July 7 (0.60’’ avg), July 12 (0.86’’ avg), July 15 (0.06’’ avg), July 27 (0.28’’ avg), July 28 (0.97’’ avg), July 30 (0.14’’ avg). Total of 7 rain events with 3.57 inches of rain this month. No Non-Compliant conditions or Water Quality violations. Ongoing sediment remediation from flood plain at Station 202 (OF15).