Monthly Construction and Environmental Update August 2009
August 31, 2009

Escatawpa to Jones Road (8,650’)
• Area stabilized with permanent BMPs.
• All grass areas mowed.

Jones Road to Walter Tanner Road (10,650’)
• Area stabilized with permanent BMPs.
• All grass areas mowed.

Walter Tanner Road to Wilmer-Georgetown Road (4,186’)
• Area stabilized with permanent BMPs.
• All grass areas mowed.

Wilmer-Georgetown Road to Glenwood Road (13,617’)
• Area stabilized with permanent BMPs.
• All grass areas mowed.

Glenwood Road to east end of project (4,964’)
• Area stabilized with permanent BMPs.
• All grass areas mowed.

Environmental Issues:
• Rain Days: Total of 18 events totaling 6.41 inches for this month.
• No Non-Compliant conditions or Water Quality violations for this month.
• Ongoing sediment remediation from flood plain at Station 202 (OF15).
• Security fencing has been installed at various locations as noted :
• Gates will be locked and accessible by ALDOT and MAWSS personnel only.
1. Fences with locked gates West of Jones Road and at west end of base and pave project.
2. Fenced and locked East of Jones Road and West of Tanner Road.
3. Fenced and locked East of Tanner Road and West of Wilmer Georgetown Road.
4. Accessible east of Wilmer Georgetown to about station 380 (where mobile home is located) south side of road. Fenced and locked from this point to east of Glenwood Road.
5. Glenwood Road is accessible for houses on south side of road. Fenced and locked from station 452 to Jersey barricades on east end of project (current point of project termination).
• Daily inspections for maintenance on going.
• Contractor has demobilized all equipment from site.