Escatawpa to Jones Road (8,650)
Area stabilized with permanent BMPs.
Jones Road to Walter Tanner Road (10,650)
Area stabilized with permanent BMPs.
Sediment Removal from floodplain at Station 202 (OF 15) is complete. Wetland vegetation is complete in the area where sediment was removed.
Walter Tanner Road to Wilmer-Georgetown Road (4,186)
Area stabilized with permanent BMPs.
Wilmer-Georgetown Road to Glenwood Road (13,617)
Area stabilized with permanent BMPs.
Glenwood Road to east end of project (4,964)
Area stabilized with permanent BMPs.
Environmental Issues:
Rain Days: Total of 10 events totaling 15.88 inches for this month.
No Non-Compliant conditions or Water Quality violations for this month.
Security fencing has been installed at various locations as noted :
Gates will be locked and accessible by ALDOT, MAWSS, and Mobile County Sherriffs Department personnel.
1. Fences with locked gates West of Jones Road and at west end of base and pave project.
2. Fenced and locked East of Jones Road and West of Tanner Road.
3. Fenced and locked East of Tanner Road and West of Wilmer Georgetown Road.
4. Accessible east of Wilmer Georgetown to about station 380 (where mobile home is located) south side of road. Fenced and locked from this point to east of Glenwood Road.
5. Glenwood Road is accessible for houses on south side of road. Fenced and locked from station 452 to Jersey barricades on east end of project (current point of project termination).
The Mobile County Sherriffs Department is patrolling the project for security.
Daily inspections for maintenance on going.
Maintenance performed as needed after storm events.
Contractor has demobilized all equipment from site.