Escatawpa to Jones Road (8,650)
Area stabilized with permanent BMPs.
Jones Road to Walter Tanner Road (10,650)
Area stabilized with permanent BMPs.
Sediment Removal from floodplain at Station 202 (OF 15) is complete. Wetland vegetation is complete in the area where sediment was removed.
Walter Tanner Road to Wilmer-Georgetown Road (4,186)
Area stabilized with permanent BMPs.
Wilmer-Georgetown Road to Glenwood Road (13,617)
Area stabilized with permanent BMPs.
Glenwood Road to east end of project (4,964)
Area stabilized with permanent BMPs.
Environmental Issues:
Rain Days: Total of 5 events totaling 6.63 inches for the month.
No Non-Compliant conditions or Water Quality violations for this month.
Security fencing maintained along project with gates for access as required.
Gates locked and accessible by ALDOT, MAWSS, and Mobile County Sherriffs Department personnel.
The Mobile County Sherriffs Department patrols the project for security.
Daily inspections for maintenance on going.
Maintenance performed as needed after storm events to correct minor washes.
ALDOT District Maintenance crews are painting exposed rebar for concrete barrier rails to be constructed when the Big Creek Bridge extension is completed.
Contractor has demobilized all equipment from site.
The sediment removal work required by ADEM has been completed and a Certification of Sediment Remediation Report has been submitted to ADEM.
.