Escatawpa to Jones Road (8,650’)
• Area stabilized with permanent BMPs.
Jones Road to Walter Tanner Road (10,650’)
• Area stabilized with permanent BMPs.
• Sediment Removal from floodplain at Station 202 (OF 15) is complete. Wetland vegetation is complete in the area where sediment was removed.
Walter Tanner Road to Wilmer-Georgetown Road (4,186’)
• Area stabilized with permanent BMPs.
Wilmer-Georgetown Road to Glenwood Road (13,617’)
• Area stabilized with permanent BMPs.
Glenwood Road to east end of project (4,964’)
• Area stabilized with permanent BMPs.

Environmental Issues:
• Rain Days: Total of 5 events totaling 6.62 inches for the month.
• No Non-Compliant conditions or Water Quality violations for this month.
• Security fencing maintained along project with gates for access as required.
• Gates locked and accessible by ALDOT, MAWSS, and Mobile County Sherriff’s Department personnel.
• The Mobile County Sherriff’s Department patrols the project for security.
• Daily inspections for maintenance on going.
• Maintenance performed as needed after storm events to correct minor washes.
• Contractor has demobilized all equipment from site.
• The sediment removal work required by ADEM has been completed and a Certification of Sediment Remediation Report has been accepted by ADEM. All requirements of the Consent Order with ADEM have been satisfied.
• ALDOT will apply for a Notice of Termination for the construction stormwater permit for the project.