Escatawpa to Jones Road (8,650)
Base and pave project through this section underway.
o A layer of soil-aggregate base has been placed over completed sub grade.
o Application of prime coat over soil-aggregate base should begin in December.
o Asphalt layer should begin in early December 2008.
Perimeter silt fences, wattles, and inlet protection devices in place for sediment control.
Jones Road to Walter Tanner (10,650)
Base and pave project through this section underway.
o A layer of soil-aggregate base has been placed over completed sub grade.
o Application of prime coat over soil-aggregate base should begin in December 2008.
Perimeter silt fences, wattles, and inlet protection devices in place for sediment control.
Grading work and slope stabilization just east of Scarbo Creek bridges should be completed by early December 2008.
Slope stabilization anchoring system for high fill sections remains in progress.
All other areas stabilized with BMPs.
Walter Tanner to Wilmer-Georgetown (4,186)
Temporary BMPs controlling erosion and sediment include -aggregate surfacing, wattles, inlet protection, slope stabilization with grassing, and rolled erosion control products.
Construction of roadways, drain pipes, and ditches from Station 270 to 280 complete.
Wilmer-Georgetown to Glenwood (13,617)
Slope issues at Long Branch have been completed with buttress and chimney drain system and area stable.
Slope issues near Station 360 have been completed with buttress and chimney drain system.
Ditch line excavation and grade work for roadway has begun around Station 385.
Glenwood to east end (4,964)
o No work this month.
o Area stabilized with temporary vegetation and BMPs.
o Future side drainage ditch lines and treatment ponds have been surveyed for each outfall in Collins Creek area in anticipation of upcoming construction.
Environmental Issues:
- Rain Days: Nov 7 (0.26 avg.), Nov 13 (0.82 avg.), Nov 24 (0.44 avg.) Total of 3 rain dates this month. No water quality violations.